Project PSE-149 — Project Summary

Queue ID
PSE-149
Capacity
200 MW
Technology
Battery
Status
active
Location
Whatcom, WA
Region
West
Developer
IA Status
Cluster Study

PSE-149

PSE-149BetaActiveBatteryPSELBNL

200 MW storage in Whatcom, WA · In queue since April 2024 · Proposed COD December 2027

200 MW

Capacity

1

Components

Battery

2y 1m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 8m

Impact Study25%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

About

PSE-149 is a proposed 200 MW battery storage project located in Whatcom County, Washington. The project, developed by Puget Sound Energy (PSE), entered the PSE interconnection queue on April 17, 2024, with a proposed commercial operation date of December 31, 2027. Its interconnection status is currently in the Cluster Study phase.

The project will interconnect at the Arco Central 115kV Substation. The development has appeared in recent news coverage regarding Puget Sound Energy's grid modernization efforts.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Whatcom

Grid Region

Mountain West

Market

Developer

Utility

Puget Sound Energy

Entity

PSE

Service Type

Point of Interconnection

Arco Central 115kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PSE-149