PSE-52
20 MW generation in Kittitas, WA · In queue since October 2017 · Proposed COD December 2025
20 MW
Capacity
1
Components
Wind
8y 7m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PSE-52 is a proposed 20 MW wind generation project located in Kittitas County, Washington. The project is sponsored by Puget Sound Energy (PSE) and interconnected to the Cascade-Rocky Reach 230 kV Line. It entered the PSE interconnection queue on October 16, 2017, with a proposed commercial operation date of December 31, 2025.
The project's interconnection status is currently listed as "suspended," and its Interconnection Agreement (IA) status is also "Suspended."
Generated from interconnection queue and public data sources
State
WA
County
Kittitas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Service Type
—
Point of Interconnection
Cascade-Rocky Reach 230 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSE-52