PSE-86
100 MW storage in Whatcom, WA · In queue since July 2020 · Proposed COD November 2023
100 MW
Capacity
1
Components
Battery
5y 10m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
3y 4m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2023-11-30
PSE-86 is a proposed 100 MW battery storage project located in Whatcom County, Washington. The project, developed by Puget Sound Energy (PSE), entered the PSE interconnection queue on July 24, 2020, and has a proposed commercial operation date of November 30, 2023. The interconnection agreement for the project has been executed.
The project will interconnect at the Portal Way 115-kV Substation.
Generated from interconnection queue and public data sources
State
WA
County
Whatcom
Grid Region
Mountain West
Market
—
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Service Type
—
Point of Interconnection
Portal Way 115-kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PSE-86