Project S-C-109 — Project Summary

Queue ID
S-C-109
Capacity
64 MW
Technology
Solar
Status
active
Location
Horry, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

S-C-109

S-C-109BetaActiveSolarS-CLBNL

64 MW generation in Horry, SC · In queue since July 2018 · Proposed COD June 2020

64 MW

Capacity

1

Components

Solar

7y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2020

Interconnection

Total Duration

1y 11m

Schedule

72 months past proposed COD

In Study38%
Queue EntryJul 6, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-06-01

About

The proposed S-C-109 project is a 64 MW solar generation project located in Horry County, South Carolina. The project is in the Santee Cooper (S-C) interconnection queue with an entry date of July 6, 2018. The proposed commercial operation date is June 1, 2020.

The interconnection agreement status is listed as "In Progress (unknown study)". The project consists of 64 MW of solar capacity. Recent news coverage of the project is unavailable.

Generated from interconnection queue and public data sources

Project Details

State

SC

County

Horry

Grid Region

Southeast

Market

Developer

Utility

Santee Cooper

Entity

S-C

Service Type

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project S-C-109