Project S-C-124 — Project Summary

Queue ID
S-C-124
Capacity
74 MW
Technology
Solar+Battery
Status
active
Location
Aiken, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

S-C-124

S-C-124BetaActiveSolarBatteryS-CLBNL

74 MW hybrid in Aiken, SC · In queue since February 2019 · Proposed COD June 2025

74 MW

Capacity

1

Components

Solar

7y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection

Total Duration

6y 4m

Schedule

11 months past proposed COD

In Study38%
Queue EntryFeb 12, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

About

Proposed project S-C-124 is a 74 MW hybrid solar and battery energy storage development in Aiken County, South Carolina. The project, located in the Southeast region, is being proposed within the Santee Cooper interconnection queue, under the queue ID S-C-124. The project consists of 74 MW of solar capacity.

The project entered the queue on February 12, 2019, with a proposed commercial operation date of June 1, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The developer is listed as entity S-C.

Generated from interconnection queue and public data sources

Project Details

State

SC

County

Aiken

Grid Region

Southeast

Market

Developer

Utility

Santee Cooper

Entity

S-C

Service Type

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project S-C-124