S-C-132
75 MW generation in Hampton, SC · In queue since December 2019 · Proposed COD May 2024
75 MW
Capacity
1
Components
Solar
6y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
4y 5m
Schedule
24 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-01
Proposed project S-C-132 is a 75 MW solar generation project located in Hampton County, South Carolina. The project is being developed within the Santee Cooper (S-C) balancing authority area. It entered the S-C interconnection queue on December 20, 2019, with a proposed commercial operation date of May 1, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists of 75 MW of solar photovoltaic generation capacity. It is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
SC
County
Hampton
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-132