S-C-165
50 MW generation in Georgetown, SC · In queue since October 2021 · Proposed COD December 2024
50 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
S-C-165 is a proposed 50 MW solar generation project located in Georgetown County, South Carolina. The project is being developed within the Santee Cooper (S-C) interconnection queue, with an entry date of October 26, 2021. The proposed commercial operation date is December 31, 2024.
The interconnection agreement for S-C-165 is currently listed as "In Progress" with an unknown study status.
Generated from interconnection queue and public data sources
State
SC
County
Georgetown
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-165