S-C-194
7 MW generation in Anderson, SC · In queue since June 2023
7 MW
Capacity
1
Components
Gas
2y 11m
In Queue
In Progress (unknown study)
IA Status
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
S-C-194 is a proposed 7 MW gas-fired generation project located in Anderson County, South Carolina. The project is being developed within the Santee Cooper (S-C) interconnection queue, with an entry date of June 1, 2023. Its interconnection agreement status is listed as "In Progress (unknown study)".
The project, filed under queue ID S-C-194, consists of 7 MW of gas-fired capacity. The proposed commercial operation date is not available.
Generated from interconnection queue and public data sources
State
SC
County
Anderson
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.