S-C-196
18 MW generation in Anderson, SC · In queue since June 2023
18 MW
Capacity
1
Components
Gas
2y 11m
In Queue
In Progress (unknown study)
IA Status
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Queue ID S-C-196 is a proposed 18 MW gas-fired generation project located in Anderson County, South Carolina. The project is being developed by Santee Cooper and is listed in the S-C interconnection queue with an entry date of June 1, 2023. Its interconnection status is currently listed as "In Progress (unknown study)".
The proposed project consists of 18 MW of gas-fired generation capacity. The project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
SC
County
Anderson
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-196