Project S-C-219 — Project Summary

Queue ID
S-C-219
Capacity
212.5 MW
Technology
Solar
Status
active
Location
Georgetown, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

S-C-219

S-C-219BetaActiveSolarS-CLBNL

212.5 MW generation in Georgetown, SC · In queue since June 2023 · Proposed COD May 2028

212.5 MW

Capacity

1

Components

Solar

2y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection

Total Duration

4y 11m

In Study38%
Queue EntryJun 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

About

S-C-219 is a proposed solar generation project with a total capacity of 212.5 MW. The project is located in Georgetown County, South Carolina, within the Southeast region. The developer is Santee Cooper (entity S-C). It consists of 212.5 MW of solar photovoltaic generation.

The project is currently active in the Santee Cooper interconnection queue, with an entry date of June 1, 2023. The proposed commercial operation date is May 1, 2028. The interconnection agreement is currently listed as "In Progress (unknown study)".

Generated from interconnection queue and public data sources

Project Details

State

SC

County

Georgetown

Grid Region

Southeast

Market

Developer

Utility

Santee Cooper

Entity

S-C

Service Type

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project S-C-219