S-C-222
74.5 MW storage in Colleton, SC · In queue since June 2023 · Proposed COD June 2028
74.5 MW
Capacity
1
Components
Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
A proposed 74.5 MW battery storage project, identified as S-C-222, is under development in Colleton County, South Carolina. The project is located in the Southeast region and is being managed within the Santee Cooper interconnection queue, under the queue ID S-C-222. The project entered the queue on June 1, 2023, with a proposed commercial operation date of June 30, 2028.
The interconnection agreement (IA) for the project is currently listed as "In Progress (unknown study)". The developer is listed as S-C. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
State
SC
County
Colleton
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-222