S-C-234
75 MW storage in Hampton, SC · In queue since June 2023 · Proposed COD October 2027
75 MW
Capacity
1
Components
Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
S-C-234 is a proposed 75 MW battery storage project located in Hampton County, South Carolina. The project is being developed within the Santee Cooper (S-C) interconnection queue, with an initial queue entry date of June 1, 2023. The current interconnection status is listed as "In Progress (unknown study)".
The proposed commercial operation date (COD) for the battery storage project is October 31, 2027. The project consists of 75 MW of battery capacity.
Generated from interconnection queue and public data sources
State
SC
County
Hampton
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-234