Project S-C-239 — Project Summary

Queue ID
S-C-239
Capacity
55 MW
Technology
Solar
Status
active
Location
Marion, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

S-C-239

S-C-239BetaActiveSolarS-CLBNL

55 MW generation in Marion, SC · In queue since June 2023 · Proposed COD December 2027

55 MW

Capacity

1

Components

Solar

2y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection

Total Duration

4y 6m

In Study38%
Queue EntryJun 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

About

Queue ID S-C-239 is a proposed solar generation project located in Marion County, South Carolina. The project, with a total capacity of 55 MW, is being developed within the Santee Cooper service area. It entered the S-C interconnection queue on June 1, 2023, with a proposed commercial operation date of December 31, 2027.

The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

SC

County

Marion

Grid Region

Southeast

Market

Developer

Utility

Santee Cooper

Entity

S-C

Service Type

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project S-C-239