S-C-246
75 MW generation in Williamsburg, SC · In queue since February 2024 · Proposed COD December 2028
75 MW
Capacity
1
Components
Solar
2y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
S-C-246 is a proposed 75 MW solar generation project located in Williamsburg County, South Carolina. The project is being developed within the Santee Cooper interconnection queue, under the queue ID S-C-246. The project entered the queue on February 1, 2024, with a proposed commercial operation date of December 31, 2028.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
SC
County
Williamsburg
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-246