S-C-250
75 MW storage in Kershaw, SC · In queue since February 2024 · Proposed COD December 2028
75 MW
Capacity
1
Components
Battery
2y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
S-C-250 is a proposed 75 MW battery storage project located in Kershaw County, South Carolina. The project is being developed within the Santee Cooper (S-C) service area. It consists of a single 75 MW battery component.
The project is currently active in the S-C interconnection queue, with an entry date of February 1, 2024. The proposed commercial operation date is December 31, 2028. The interconnection agreement is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
SC
County
Kershaw
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-250