S-C-261
49.9 MW generation in Dillon, SC · In queue since May 2024 · Proposed COD May 2025
49.9 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
1 year
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-15
A proposed solar generation project, identified as S-C-261, is under development in Dillon County, South Carolina. The project, with a total capacity of 49.9 MW, is being developed within the Santee Cooper (S-C) utility territory. It consists solely of solar photovoltaic generation.
The project is currently active in the Santee Cooper interconnection queue, with an entry date of May 15, 2024. The proposed commercial operation date is May 15, 2025. The interconnection agreement is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
SC
County
Dillon
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-261