S-C-268
54.6 MW generation in Richland, SC · In queue since June 2024 · Proposed COD December 2027
54.6 MW
Capacity
1
Components
Solar
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Proposed project S-C-268 is a 54.6 MW solar generation project located in Richland County, South Carolina. The project is in the Santee Cooper interconnection queue (S-C) with an entry date of June 5, 2024, and a proposed commercial operation date of December 31, 2027. The interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists of 54.6 MW of solar photovoltaic generation capacity. The project is currently listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
SC
County
Richland
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-268