S-C-272
74.9 MW generation in Orangeburg, SC · In queue since June 2024 · Proposed COD June 2028
74.9 MW
Capacity
1
Components
Solar
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
S-C-272 is a proposed solar generation project with a total capacity of 74.9 MW, located in Orangeburg County, South Carolina. The project is listed in the Santee Cooper interconnection queue as of June 5, 2024, with a proposed commercial operation date of June 1, 2028. The interconnection agreement status is currently "In Progress (unknown study)".
The development project is listed in the S-C queue. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
State
SC
County
Orangeburg
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-272