S-C-279
65 MW hybrid in Allendale, SC · In queue since June 2024 · Proposed COD August 2028
65 MW
Capacity
1
Components
Solar
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
A proposed 65 MW solar and battery hybrid project, identified as S-C-279, is under development in Allendale County, South Carolina. The project, consisting of a 65 MW solar component, is in the Santee Cooper (S-C) interconnection queue with an entry date of June 5, 2024. Its proposed commercial operation date is August 1, 2028.
The interconnection agreement for project S-C-279 is currently listed as "In Progress (unknown study)". The project is located in the Southeast region. Recent news coverage of the project is not available.
Generated from interconnection queue and public data sources
State
SC
County
Allendale
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project S-C-279