S-C-281
150 MW generation in Aiken, SC · In queue since June 2024 · Proposed COD June 2028
150 MW
Capacity
1
Components
Solar
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Proposed project S-C-281 is a 150 MW solar generation project located in Aiken County, South Carolina, within the Southeast region. The project is listed in the Santee Cooper (S-C) interconnection queue with an entry date of June 5, 2024. The proposed commercial operation date is June 30, 2028.
The interconnection agreement status is listed as "In Progress (unknown study)". The developer is unknown.
Generated from interconnection queue and public data sources
State
SC
County
Aiken
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.