SMUD-10
170 MW hybrid in Sacramento, CA · In queue since March 2021 · Proposed COD January 2028
170 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-04
SMUD-10 is a proposed 170 MW hybrid solar and battery project located in Sacramento County, California. The project, under development by the Sacramento Municipal Utility District (SMUD), consists of 170 MW of solar generation. It is currently listed as active in the Sacramento Municipal Utility District interconnection queue, with an entry date of March 16, 2021.
The proposed commercial operation date for SMUD-10 is January 4, 2028. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is the Cordova 230kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CA
County
Sacramento
Grid Region
Mountain West
Market
—
Developer
—
Utility
Sacramento Municipal Utility District
Entity
SMUD
Service Type
—
Point of Interconnection
Cordova 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.