SMUD-12
250 MW hybrid in Sacramento, CA · In queue since May 2021 · Proposed COD December 2027
250 MW
Capacity
1
Components
Solar
5 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
SMUD-12 is a proposed 250 MW hybrid solar and battery project located in Sacramento County, California. The development project consists of 250 MW of solar generation. It is listed in the Sacramento Municipal Utility District (SMUD) interconnection queue with an entry date of May 20, 2021, and a proposed commercial operation date of December 31, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Q3 new switching station near Cordova 230kV Substation.
Generated from interconnection queue and public data sources
State
CA
County
Sacramento
Grid Region
Mountain West
Market
—
Developer
—
Utility
Sacramento Municipal Utility District
Entity
SMUD
Service Type
—
Point of Interconnection
Q3 new switching station near Cordova 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.