SMUD-15
100 MW storage in Sacramento, CA · In queue since December 2021 · Proposed COD October 2027
100 MW
Capacity
1
Components
Battery
4y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-28
SMUD-15 is a proposed 100 MW battery storage project located in Sacramento County, California. The project is being developed within the Sacramento Municipal Utility District (SMUD) service area. It entered the SMUD interconnection queue on December 10, 2021, with a proposed commercial operation date of October 28, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 100 MW of battery storage capacity. The point of interconnection is the Franklin 230kV Substation. The project has appeared in recent news coverage regarding SMUD's grid-scale battery storage plans.
Generated from interconnection queue and public data sources
State
CA
County
Sacramento
Grid Region
Mountain West
Market
—
Developer
—
Utility
Sacramento Municipal Utility District
Entity
SMUD
Service Type
—
Point of Interconnection
Franklin 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN