SMUD-16
204 MW storage in Sacramento, CA · In queue since January 2022 · Proposed COD June 2027
204 MW
Capacity
1
Components
Battery
4y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
SMUD-16 is a proposed 204 MW battery storage project located in Sacramento County, California. The project, developed by Sacramento Municipal Utility District (SMUD), consists of 204 MW of battery capacity. It is currently in the Sacramento Municipal Utility District interconnection queue, with an entry date of January 21, 2022.
The proposed commercial operation date for SMUD-16 is June 30, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection is a new switching station near the Campbells Soup 230kV Substation.
Generated from interconnection queue and public data sources
State
CA
County
Sacramento
Grid Region
Mountain West
Market
—
Developer
—
Utility
Sacramento Municipal Utility District
Entity
SMUD
Service Type
—
Point of Interconnection
New switching station near Campbells Soup 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.