SMUD-30
156 MW hybrid in Sacramento, CA · In queue since December 2022 · Proposed COD September 2029
156 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-15
SMUD-30 is a proposed 156 MW hybrid solar and battery project located in Sacramento County, California. The project, under development by Sacramento Municipal Utility District (SMUD), consists of 156 MW of solar generation. It is listed in the Sacramento Municipal Utility District interconnection queue as of December 12, 2022, with a proposed commercial operation date of September 15, 2029. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for SMUD-30 is the Proposed Country Acres 230 kV (Q8) substation. This development project has appeared in recent news coverage regarding SMUD's renewable energy expansion plans.
Generated from interconnection queue and public data sources
State
CA
County
Sacramento
Grid Region
Mountain West
Market
—
Developer
—
Utility
Sacramento Municipal Utility District
Entity
SMUD
Service Type
—
Point of Interconnection
Proposed Country Acres 230 kV (Q8)
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.