SOCO-IC-1006
300 MW hybrid in Liberty, GA · In queue since December 2021 · Proposed COD January 2026
300 MW
Capacity
2
Components
Solar + Battery
4y 5m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
4y 1m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-15
SOCO-IC-1006 is a proposed 300 MW hybrid solar and battery project located in Liberty County, Georgia. The development project, consisting of 150 MW of solar and 150 MW of battery storage, is being proposed by Southern Company (SOCO).
The project is currently active in the Southern Company (SOCO) interconnection queue, with an entry date of December 23, 2021. The proposed commercial operation date is January 15, 2026. The interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Ludowici Primary - Riceboro 115 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Liberty
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Ludowici Primary - Riceboro 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN