SOCO-IC-1013
400 MW hybrid in Oglethorpe, GA · In queue since January 2022 · Proposed COD November 2025
400 MW
Capacity
2
Components
Solar + Battery
4y 4m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
3y 10m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-30
SOCO-IC-1013 is a proposed 400 MW hybrid solar and battery project located in Oglethorpe County, Georgia. The development project consists of 200 MW of solar generation paired with 200 MW of battery energy storage. The project is listed in the Southern Company (SOCO) interconnection queue with an entry date of January 27, 2022, and a proposed commercial operation date of November 30, 2025.
The interconnection status for SOCO-IC-1013 is currently listed as "Suspended." The point of interconnection is the East Watkinsville - Russell Dam (USA) 230 kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Oglethorpe
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
East Watkinsville - Russell Dam (USA) 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1013