SOCO-IC-1024
300 MW hybrid in Taylor, GA · In queue since February 2022 · Proposed COD June 2024
300 MW
Capacity
2
Components
Solar + Battery
4y 3m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
2y 4m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-06-30
SOCO-IC-1024 is a proposed 300 MW hybrid solar and battery project located in Taylor County, Georgia. The project, in the Southeast region, consists of a 200 MW solar component and a 100 MW battery energy storage system. It is being developed within the Southern Company (SOCO) utility territory.
The project is listed in the SOCO interconnection queue as entry SOCO-IC-1024, with a queue entry date of February 25, 2022. The proposed commercial operation date is June 30, 2024, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the Patsiliga Creek Substation 230 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Taylor
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Patsiliga Creek Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1024