SOCO-IC-1037
150 MW generation in Taliaferro, GA · In queue since May 2022 · Proposed COD April 2026
150 MW
Capacity
1
Components
Solar
4 years
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
3y 11m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-13
SOCO-IC-1037 is a proposed solar generation project located in Taliaferro County, Georgia, within the Southeast region. The development project, with a total capacity of 150 MW, is being pursued by Southern Company (SOCO). It consists of 150 MW of solar photovoltaic generation.
The project is currently active in the Southern Company (SOCO) interconnection queue, with an entry date of May 19, 2022. Its proposed commercial operation date is April 13, 2026. The interconnection agreement (IA) status is currently listed as Suspended.
Generated from interconnection queue and public data sources
State
GA
County
Taliaferro
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Ray Place Road - Union Point Primary 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1037