SOCO-IC-1040
170 MW hybrid in Hale, AL · In queue since June 2022 · Proposed COD February 2027
170 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-01
SOCO-IC-1040 is a proposed 170 MW solar and battery hybrid project located in Hale County, Alabama. The development project, under the utility Southern Company (SOCO), consists of 170 MW of solar capacity. It is currently listed as active in the Southern Company (SOCO) interconnection queue with an entry date of June 29, 2022.
The proposed commercial operation date (COD) for SOCO-IC-1040 is February 1, 2027. The project's interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Greene County - Moundville TS 230 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Hale
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Greene County - Moundville TS 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.