SOCO-IC-1042
200 MW hybrid in Rockdale, GA · In queue since July 2022 · Proposed COD March 2026
200 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
3y 8m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-31
SOCO-IC-1042 is a proposed 200 MW hybrid solar and battery energy storage project located in Rockdale County, Georgia. The project, located in the Southeast region, is being developed within the Southern Company (SOCO) utility territory. The interconnection request was filed on July 11, 2022, with a proposed commercial operation date of March 31, 2026.
The project consists of a 200 MW battery energy storage system co-located with a solar facility. It is listed in the Southern Company interconnection queue as SOCO-IC-1042, and its interconnection agreement (IA) status is currently suspended. The point of interconnection (POI) is the Conyers 115 kV Transmission Substation (TS).
Generated from interconnection queue and public data sources
State
GA
County
Rockdale
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Conyers 115 kV TS
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN