SOCO-IC-1051
80 MW generation in Escambia, AL · In queue since August 2022 · Proposed COD May 2027
80 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-15
SOCO-IC-1051 is a proposed solar generation project with a total capacity of 80 MW, located in Escambia County, Alabama. The project is being developed within the Southern Company (SOCO) service area. It consists of 80 MW of solar photovoltaic generation.
The project is currently in the Southern Company interconnection queue (SOCO-IC-1051), with an entry date of August 21, 2022. The proposed commercial operation date is May 15, 2027. The interconnection agreement (IA) status is currently listed as Suspended.
Generated from interconnection queue and public data sources
State
AL
County
Escambia
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Bucks SS - North Brewton 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1051