SOCO-IC-1055
200 MW generation in Coffee, GA · In queue since August 2022 · Proposed COD October 2027
200 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-10-01
SOCO-IC-1055 is a proposed solar generation project with a total capacity of 200 MW, located in Coffee County, Georgia. The project is being developed within the Southern Company (SOCO) service area. It consists of 200 MW of solar photovoltaic generation.
The project is listed in the SOCO interconnection queue as of August 26, 2022, with a proposed commercial operation date of October 1, 2027. The interconnection agreement (IA) for the project has been executed. The point of interconnection (POI) is the Douglas - Kettle Creek Primary 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Coffee
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Douglas - Kettle Creek Primary 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1055