SOCO-IC-1061
160 MW hybrid in Marengo, AL · In queue since September 2022 · Proposed COD April 2027
160 MW
Capacity
2
Components
Solar + Battery
3y 8m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-02
SOCO-IC-1061 is a proposed 160 MW hybrid solar and battery project located in Marengo County, Alabama. The development project, filed by Southern Company (SOCO), consists of 80 MW of solar capacity paired with 80 MW of battery storage. It is currently listed as active in the Southern Company (SOCO) interconnection queue, with an entry date of September 7, 2022, and a proposed commercial operation date of April 2, 2027.
The project's interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Bellamy - Demopolis 115 kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AL
County
Marengo
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Bellamy - Demopolis 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.