SOCO-IC-1066
80 MW generation in Dale, AL · In queue since September 2022 · Proposed COD August 2030
80 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Suspended
IA Status
COD target: 2030
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-08-15
SOCO-IC-1066 is a proposed solar generation project located in Dale County, Alabama. The project, with a total capacity of 80 MW, is being developed by SOCO, a subsidiary of Southern Company. It consists of 80 MW of solar photovoltaic generation.
The project is currently in the Southern Company (SOCO) interconnection queue, with an entry date of September 9, 2022. The proposed commercial operation date is August 15, 2030. The interconnection agreement status is currently listed as Suspended. The point of interconnection is the Dothan - Pinckard No. 2 115 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Dale
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Dothan - Pinckard No. 2 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.