SOCO-IC-1068
248 MW hybrid in Emanuel, GA · In queue since September 2022 · Proposed COD July 2027
248 MW
Capacity
2
Components
Solar + Battery
3y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-07-01
SOCO-IC-1068 is a proposed hybrid solar and battery project located in Emanuel County, Georgia. The development project, with a total capacity of 248 MW, consists of 124 MW of solar generation and a 124 MW battery energy storage system. The project is being developed within the Southern Company (SOCO) service area.
The project is listed in the SOCO interconnection queue with an entry date of September 20, 2022, and a proposed commercial operation date of July 1, 2027. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Vidalia - Wadley Primary (Black) 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Emanuel
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Vidalia - Wadley Primary (Black) 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1068