SOCO-IC-1074
110.5 MW generation in Turner, GA · In queue since October 2022 · Proposed COD August 2025
110.5 MW
Capacity
1
Components
Solar
3y 7m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
2y 10m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-08-15
SOCO-IC-1074 is a proposed solar generation project with a total capacity of 110.5 MW. The project is located in Turner County, Georgia, within the Southeast region, and is being developed by Southern Company (SOCO). It consists of 110.5 MW of solar photovoltaic generation.
The project is listed in the Southern Company (SOCO) interconnection queue with an entry date of October 5, 2022. The proposed commercial operation date is August 15, 2025, and the Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is the North Tifton - Pitts 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Turner
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Tifton - Pitts 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1074