SOCO-IC-1075
80 MW generation in Dallas, AL · In queue since October 2022 · Proposed COD July 2027
80 MW
Capacity
1
Components
Solar
3y 7m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-15
SOCO-IC-1075 is a proposed 80 MW solar generation project located in Dallas County, Alabama. The project is being developed by SOCO, a subsidiary of Southern Company. It consists of 80 MW of solar photovoltaic generation.
The project is currently active in the Southern Company (SOCO) interconnection queue, with an interconnection request date of October 5, 2022, and a proposed commercial operation date of July 15, 2027. The interconnection agreement for the project has been executed. The point of interconnection is the Millers Ferry Dam (COE) - Selma 115 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Dallas
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Millers Ferry Dam (COE) - Selma 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1075