SOCO-IC-1086
160 MW hybrid in Perry, AL · In queue since November 2022 · Proposed COD July 2026
160 MW
Capacity
2
Components
Solar + Battery
3y 6m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-15
SOCO-IC-1086 is a proposed 160 MW hybrid solar and battery project located in Perry County, Alabama. The development project, with Southern Company (SOCO) as the interconnecting entity, consists of 80 MW of solar capacity coupled with 80 MW of battery storage. It is listed as active in the Southern Company (SOCO) interconnection queue with an entry date of November 2, 2022.
The proposed commercial operation date for SOCO-IC-1086 is July 15, 2026. The interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Greene County - North Selma 230 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Perry
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Greene County - North Selma 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1086