SOCO-IC-1089
125 MW generation in Perry, MS · In queue since November 2022 · Proposed COD July 2027
125 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
SOCO-IC-1089 is a proposed solar generation project with a total capacity of 125 MW, located in Perry County, Mississippi. The project is being developed within the Southern Company (SOCO) service area. It entered the SOCO interconnection queue on November 9, 2022, and has a proposed commercial operation date of July 1, 2027. The interconnection agreement (IA) status for the project is currently listed as Suspended. The point of interconnection (POI) is the Eaton - Lucedale 115 kV Line.
The development project consists of 125 MW of solar photovoltaic generation. It is currently listed as an active project in the interconnection queue. Recent news coverage has discussed the project's potential impact on the regional energy market.
Generated from interconnection queue and public data sources
State
MS
County
Perry
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Eaton - Lucedale 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1089