SOCO-IC-1094
200 MW generation in Irwin, GA · In queue since November 2022 · Proposed COD June 2026
200 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-15
SOCO-IC-1094 is a proposed solar generation project with a total capacity of 200 MW, located in Irwin County, Georgia. The developer is Southern Company (SOCO). The project is listed in the Southern Company (SOCO) interconnection queue as of November 22, 2022, with a proposed commercial operation date of June 15, 2026. Its interconnection agreement (IA) status is currently listed as Suspended.
The point of interconnection (POI) for SOCO-IC-1094 is the North Tifton - Stump Creek 230 kV Line. The project consists of 200 MW of solar photovoltaic generation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Irwin
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Tifton - Stump Creek 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.