Project SOCO-IC-1098 — Project Summary

Queue ID
SOCO-IC-1098
Capacity
225 MW
Technology
Solar
Status
active
Location
Taylor, GA
Region
Southeast
Developer
IA Status
Suspended

SOCO-IC-1098

SOCO-IC-1098BetaActiveSolarSOCOLBNL

225 MW generation in Taylor, GA · In queue since November 2022 · Proposed COD June 2027

225 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Suspended

IA Status

COD target: 2027

Interconnection

Total Duration

4y 7m

In Study38%
Queue EntryNov 25, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-15

About

SOCO-IC-1098 is a proposed solar generation project with a total capacity of 225 MW, located in Taylor County, Georgia. The project is being developed within the Southern Company (SOCO) service area. It entered the SOCO interconnection queue on November 25, 2022, with a proposed commercial operation date of June 15, 2027. The point of interconnection is the Butler DS Substation 230 kV Bus. Its interconnection agreement status is currently listed as Suspended.

The proposed project consists of 225 MW of solar photovoltaic generation. It is listed in the interconnection queue of the Southern Company (SOCO). The project has appeared in recent news coverage regarding renewable energy development in the Southeast region.

Generated from interconnection queue and public data sources

Project Details

State

GA

County

Taylor

Grid Region

Southeast

Market

Developer

Utility

Southern Company

Entity

SOCO

Service Type

Point of Interconnection

Butler DS Substation 230 kV Bus

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SOCO-IC-1098