SOCO-IC-1098
225 MW generation in Taylor, GA · In queue since November 2022 · Proposed COD June 2027
225 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-15
SOCO-IC-1098 is a proposed solar generation project with a total capacity of 225 MW, located in Taylor County, Georgia. The project is being developed within the Southern Company (SOCO) service area. It entered the SOCO interconnection queue on November 25, 2022, with a proposed commercial operation date of June 15, 2027. The point of interconnection is the Butler DS Substation 230 kV Bus. Its interconnection agreement status is currently listed as Suspended.
The proposed project consists of 225 MW of solar photovoltaic generation. It is listed in the interconnection queue of the Southern Company (SOCO). The project has appeared in recent news coverage regarding renewable energy development in the Southeast region.
Generated from interconnection queue and public data sources
State
GA
County
Taylor
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Butler DS Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1098