SOCO-IC-1101
225 MW hybrid in Perry, AL · In queue since December 2022 · Proposed COD May 2027
225 MW
Capacity
2
Components
Solar + Battery
3y 5m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-31
SOCO-IC-1101 is a proposed 225 MW hybrid solar and battery project located in Perry County, Alabama. The development project, consisting of 150 MW of solar capacity and 75 MW of battery storage, is being proposed by Southern Company (SOCO).
The project is currently in the SOCO interconnection queue with an entry date of December 6, 2022. The proposed commercial operation date is May 31, 2027, and the interconnection agreement status is currently listed as Suspended. The point of interconnection is the Greene County - North Selma 230 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Perry
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Greene County - North Selma 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1101