SOCO-IC-1113
200 MW generation in Lamar, MS · In queue since January 2023 · Proposed COD November 2027
200 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-01
SOCO-IC-1113 is a proposed 200 MW solar generation project located in Lamar County, Mississippi. The project is being developed by Southern Company (SOCO) and interconnected to the Hattiesburg Southwest - Adams Creek 230 kV Line. It entered the SOCO interconnection queue on January 9, 2023, with a proposed commercial operation date of November 1, 2027. Its interconnection agreement status is currently listed as Suspended.
The project consists of 200 MW of solar photovoltaic generation capacity. It is listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
MS
County
Lamar
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Hattiesburg Southwest - Adams Creek 230 kV LIne
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1113