SOCO-IC-1122
79.9 MW generation in Montgomery, AL · In queue since March 2023 · Proposed COD September 2027
79.9 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-30
SOCO-IC-1122 is a proposed solar generation project located in Montgomery County, Alabama, with a total capacity of 79.9 MW. The developer is Southern Company (SOCO). The project consists of 79.9 MW of solar photovoltaic generation. It is currently listed as active in the Southern Company (SOCO) interconnection queue, with a queue entry date of March 1, 2023, and a proposed commercial operation date of September 30, 2027. The interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Pike County - Snowdoun 230 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Montgomery
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Pike County - Snowdoun 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.