SOCO-IC-1145
156 MW generation in Jasper, MS · In queue since June 2023 · Proposed COD November 2028
156 MW
Capacity
1
Components
Solar
2y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-11-06
SOCO-IC-1145 is a proposed solar generation project with a total capacity of 156 MW, located in Jasper County, Mississippi, within the Southeast region. The project is being developed by SOCO, a subsidiary of Southern Company. It consists of 156 MW of solar photovoltaic generation.
The project is currently active in the Southern Company (SOCO) interconnection queue, with an entry date of June 9, 2023. The proposed commercial operation date is November 6, 2028, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the Jasper East SS Substation 230 kV Bus.
Generated from interconnection queue and public data sources
State
MS
County
Jasper
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Jasper East SS Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.