SOCO-IC-1153
150 MW generation in Wilcox, GA · In queue since July 2023 · Proposed COD April 2027
150 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
SOCO-IC-1153 is a proposed solar generation project with a total capacity of 150 MW, located in Wilcox County, Georgia. The project is being developed within the Southern Company (SOCO) service area. It entered the SOCO interconnection queue on July 18, 2023, with a proposed commercial operation date of April 1, 2027. Its interconnection agreement (IA) status is currently listed as Suspended.
The proposed project consists of 150 MW of solar photovoltaic generation. The point of interconnection (POI) is the Kathleen - Pitts 230 kV Line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
GA
County
Wilcox
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Kathleen - Pitts 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1153