SOCO-IC-1166
411 MW generation in Coweta, GA · In queue since August 2023 · Proposed COD December 2025
411 MW
Capacity
1
Components
Gas
2y 9m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
2y 4m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2025-12-01
SOCO-IC-1166 is a proposed 411 MW gas-fired generation project located in Coweta County, Georgia. The project is being developed by Southern Company (SOCO). It entered the SOCO interconnection queue on August 11, 2023, with a proposed commercial operation date of December 1, 2025. The interconnection agreement for the project has been executed.
The point of interconnection for SOCO-IC-1166 is the Yates 6 & 7 Substation 230 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Coweta
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Yates 6 & 7 Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1166