SOCO-IC-1167
822 MW generation in Coweta, GA · In queue since August 2023 · Proposed COD December 2025
822 MW
Capacity
1
Components
Gas
2y 9m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
2y 4m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2025-12-01
SOCO-IC-1167 is a proposed 822 MW gas-fired generation project located in Coweta County, Georgia. The project is being developed by Southern Company (SOCO) and is interconnected within the Southern Company (SOCO) queue. The project entered the queue on August 11, 2023, and has a proposed commercial operation date of December 1, 2025.
The interconnection agreement for SOCO-IC-1167 has been executed. The point of interconnection is the Yates 6 & 7 Substation 230 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Coweta
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Yates 6 & 7 Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.