SOCO-IC-1172
127.5 MW generation in Jefferson, GA · In queue since September 2023 · Proposed COD May 2027
127.5 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-31
SOCO-IC-1172 is a proposed solar generation project with a total capacity of 127.5 MW. The project is located in Jefferson County, Georgia, within the Southeast region, and is being developed by Southern Company (SOCO). It consists of 127.5 MW of solar photovoltaic generation.
The project is currently in the Southern Company interconnection queue as entry SOCO-IC-1172, with a queue entry date of September 8, 2023. The proposed commercial operation date is May 31, 2027. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Sandersville #1 - Wadley Primary 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Jefferson
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Sandersville #1 - Wadley Primary 230 kV LIne
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.